Construction Updates

Building Progress and Timelines

We know construction can be disruptive sometimes. To help you plan ahead, here are a few quick updates about our Lighthouse development and what you can expect.

Construction Hours

Data Center Campus Construction Hours:

Monday – Friday: 6 AM to 8 PM

Saturday:
6 AM to 8 PM

STAY InFORMED

For construction or safety concerns, please contact us.

August Summary

Construction continues to progress steadily across the campus. Residents and visitors may notice ongoing truck traffic, earthmoving equipment and daytime construction noise as crews install utilities and advance work throughout the site.

Several buildings have entered the interior construction phase. As work moves indoors, there will generally be less visible activity around those buildings. Other structures remain in earlier stages of construction, where crews continue installing structural steel, pouring concrete and completing other large-scale construction activities.

Most construction and utility work remains within the project site, and all construction vehicles continue to use designated haul routes. As work progresses, residents will begin to see more completed building exteriors, newly paved areas and landscaping throughout the campus.

Traffic Updates

In August, crews will install temporary traffic signals at the Interstate 43 and Highway H interchange (Exit 100). The signals are expected to become operational later this month.

Please use caution when traveling through the intersection and allow extra time to become familiar with the new traffic pattern.

Construction-related traffic will continue along County Road LL. Drivers should expect increased activity near the intersections of Highland Lane and Lake Drive and should use additional caution when traveling through those areas.

Campus Progress

  • The campus includes four single-story data center buildings. 
  • Two data center buildings are fully enclosed and have transitioned to the interior construction phase. 
  • The remaining two buildings continue through the structural construction phase, with crews actively installing building frameworks.